Following the Kisvárda Stadium project, we were faced with another challenge, this time almost twice as large, but our team arrived well-prepared for the task.
Naturally, challenges arise in every project. On-site, the tight deadline was perhaps the most difficult for everyone, but we managed to deliver the infrastructure on time. Over 3 kilometers of triax, 2 kilometers of SMPTE, and several hundred meters of 12-core multi- and single-mode optical cables were installed between the broadcast compound and the endpoints. This setup included the commentator positions, the reporting location, the technical room, and 12 camera positions, ensuring a comprehensive broadcast infrastructure that supports high-quality production and coverage.